EFFECTIVE NEW TECHNIQUES
FOR
DISCHARGE OF STATIC
ELECTRICITY ON INNER AND
OUTER
PIPE SURFACES
Sponsored by
Gas
Research Institute
GRI
Contract No. 5089-271-1877
Presented by
Oren
Tranbarger
Southwest Research Institute
(512)
522-2710
Presented at
GRI
WORKSHOP ON PLASTIC PIPE RESEARCH RESULTS
September 30 – October 1, 1992
GRI
Principal Manager
Dr.
Michael M Mamoun
(312)
399-8212
EFFECTIVE NEW TECHNIQUES FOR DISCHARGE OF STATIC ELECTRICITY ON INNER AND OUTER
PIPE SURFACES
O.
Tranbarger – Southwest Research Institute______________________________________
ABSTRACT
Whenever high-velocity particulates, such as dust or iron-oxide, hit the
interior wall of polyethylene (PE) pipe, electrostatic charge is generated by
triboelectrification (friction or contact charging).
The interior charge will reside indefinitely within the pipe because of
the high resistivity of PE. The
presence of interior charge produces exterior charge, which may result in a
problem in cutting the pipe for repairs.
In both cases, a spark discharge can occur from:
(1) the exterior surfaces to nearby grounded objects; or (2) a grounded
cutter penetrating the pipe wall. A
spark discharge in a flammable gas-air mixture produces an explosion or fire and
must be avoided at all costs.
To neutralize charge buildup, the surface resistivity must be lowered to
be slightly conductive so that counter charge can flow from ground.
This is easily accomplished externally by wrapping the pipe with
conductive material or wetting. The
interior charge problem requires that the pipe wall be penetrated with a
grounded metallic cutter and spraying apparatus.
This project has resulted in materials, equipment, and procedures for
neutralizing both the internal and external charge accumulations.
An antistatic PE film wrap is used to replace the wet soapy burlap wrap
presently used in the industry.
This is a dry process that eliminates:
(1) the mess in the trench from frequent wetting applications; (2) the
freezing problem; and (3) the evaporation problem encountered using the burlap
wrap. For the internal problem, a
standard tapping saddle was modified and fitted with a spraying apparatus to
coat the interior of the pipe with an antistatic spray.
The antistatic fluid developed for the discharger also can be used on the
exterior of the pipe for effective wetting.
INTRODUCTION
Charge
Problem
During leak repairs of PE pipe, serious electrostatic problems can occur
because of triboelectrification (frictional charging) that produces charge
buildup on the inside and outside surfaces of the pipe.
If the charge buildup is sufficient, a spark discharge can ignite a
flammable gas-air mixture, or cause electrical shock to personnel near a charged
pipe surface, or produce a pinhole1 in the wall of the pipe.
Spark discharges may have been the cause of ignition in several serious
incidents and fatality2 cases that have occurred while repairing PE
pipe. Squeeze-off operations combined
with particulates in the gas and contamination within the pipe contribute to the
charge problem. Even under
apparently normal operations when the pipe is not being squeezed, pinholing is
observable because of high-turbulent flow conditions occurring near
Charge
Removal Procedures
A
common procedure used to reduce the electrostatic hazard is to wet the outside
surface of the pipe. The gas
industry currently uses a wet soapy (surfactant) burlap wrap3 or tape
to make the pipe slightly conductive to neutralize excess exterior charge. This
procedure is beneficial; however, this exterior treatment of the pipe does not
reduce the interior charge buildup.
Until the new technology was developed for GRI, no effective method existed for
neutralizing charge inside plastic pipe, although this is a more serious problem
than exterior surface charge accumulations.
The interior charge problem is evident after gas flow has been cut off,
and a defective section of pipe is cut by suing a saw or circular cutter.
When a metal object penetrates the inner wall of a charged pipe, a spark
discharge is inevitable.
GRI
Project
Because of the serous electrostatic problems of PE pipe, GRI recently initiated
a research project to develop methods and techniques for discharging PE pipe to
eliminate the spark-discharge hazard.
This project has been a joint effort with the Brooklyn Union Gas Company
as a co-funder.
Project Objectives
The
primary objective of the project was to develop a practical prototype
electrostatic discharger that can neutralize charge accumulations inside PE pipe
used for gas distribution systems.
Secondary objectives included: (1)
developing an improved method for dissipating charge accumulations on the
outside surface of PE pipe; (2) developing instrumentation for measuring the
electrostatic voltages on the inside and outside surfaces of PE pipe; and (3)
investigating methods for improving PE pipe manufacturing to avoid electrostatic
charge buildup.
Discussion
The following discussion presents some of the research results pertaining
to: (1) the electrostatic discharge of PE pipe; (2) instrumentation used for
assessing charge conditions of PE pipe; (3) the test facilities constructed for
charging PE pipe; and (4) laboratory and filed test data.
GAS
INDUSTRY NEEDS
When a repair crew arrives at the scene of leak, the first item needed is
an electric fieldmeter to determine if charge is present.
The second need is for an internal discharger to neutralize the charge
source. The third need is a method
to neutralize the external charge problem and eliminate problems encountered
using the wet, soapy burlap wrap.
Frequent wetting can produce muddy conditions in the trench.
In freezing weather, the soapy solution can freeze.
Evaporation occurs in hot weather.
DISCHARGING PRINCIPLES AND PROBLEMS
Because electrostatic charges are immobile on high-resistivity PE surfaces, the
surface resistivity must be lowered so that counter charge can be supplied from
a ground path. By making the
surfaces slightly conductive, charges can be redistributed so that high-value
point sources are eliminated, and charge mobility is then possible for
neutralization from counter charge flowing from ground.
In the case of internal charge, a surfactant is used to uniformly coat
and wet the surface; thereby, lowering the surface resistivity.
Counter charge is provided through the cutting tool that penetrates the
pipe, which is grounded. The
antistatic fluid used to coat the inside of the pipe also provides the
conductive path between the inside surface and the cutter.
Exterior discharging must be accomplished through a high-resistivity path
to prevent any spark discharges that might ignite a flammable gas-air mixture.
The antistatic PE wrap meets this criterion; and therefore, is sparkless
and safe to use for the external problem.
One method usually suggested for discharging is a wire inserted into the
pipe or spiral wrapped externally.
This method is not applicable to the pipe problem because of charge immobility.
Because of the high resistivity of PE and limited surface area of the
wire, no current flows between a point charge on the surface and a ground wire.
Noncontacting radioactive and X-ray sources can result in charge
neutralization but are impractical because of: (1) real or perceived health
hazards; (2) size; (3) weight; and (4) cost.
INSTRUMENTATION PRINCIPLES AND PROBLEMS
The
theoretical nature of the charge problem makes practical instrumentation for
accurately assessing the charge conditions inside a plastic pipe difficult.
Because opposite-polarity charge can accumulate on the inside and outside
pipe surfaces, cancellation or the electric filed produces masking effects.
If the charges inside and outside are equal in magnitude and opposite in
polarity, the net external electric field is zero.
However, under these conditions, the electric field within the pipe wall
is the highest possible. Therefore,
a zero net electric field does not imply a charge-free condition.
Although theoretical problems hamper the true assessment of the charge
conditions, any electric field detectable external to the pipe implies that a
charge problem exits.
If a charge-free surface can be maintained on the outside pipe surfaces,
then a Faraday cage can be used to assess the voltage inside the pipe.
A Faraday cage is a metallic coaxial cylinder (closed shield) around the
pipe that has an electric field sensor mounted in the outside wall at the
center.
SOLUTIONS
Internal Discharger
Until
this project no internal discharger was available for neutralizing PE gas pipe.
The internal discharger uses a self-tapping saddle fitting to deliver
antistatic fluid in the interior of the pipe.
A clamp-on saddle is used for the discharger, which can be mounted and
removed very quickly.
External Discharging
The solution for the external discharging problem is to wrap the pipe
using antistatic treated PE film that has a high resistivity but which is
conductive enough to dissipated charge effectively through a ground path.
In addition to the PE wrap, the outside of the pipe can be sprayed with
the antistatic spray developed on the project, which does not freeze or
evaporate.
Instrumentation
Hand-held electric fieldmeters (voltmeters) are commercially available to meet
some of the instrumentation needs.
However, these instruments cannot be used for any quantitative measurements,
since induced charge on the exterior of the pipe masks the effects of any
internal charge. Because of masking
effects, high electric field conditions can exist in the wall of the pipe
although the net external electric field is zero.
Since a zero-field measurement does not necessarily imply a charge-free
pipe, a charge problem would exist if any charge is detected.
Quantitative measurements can be made using a Faraday cage or a closed
coaxial cylinder around the pipe, providing the exterior of the pipe is neutral
prior to a measurement or test. The
Faraday cage is strictly a laboratory instrument and could not be implemented in
a practical fieldable system.
A flat plate sensor also can be used for observing any external electric
field emanating from a pipe. This
type of instrument is useful in wrap tests.
In operation, it is very similar to the hand-held devices and has the
same limitations due to masking effects.
Antistatic Fluid
One component of the internal discharger is the antistatic fluid that:
(1) is effective down to -20oF; (2) does not evaporate; and
(3) is safe for use on PE surfaces without accelerating crack growth.
The antistatic fluid also can be sued for external applications with the
PE wrap.
Laboratory And Field Tests
Numerous laboratory tests and four pilot field tests on actual gas lines were
conducted to validate the internal discharger and the techniques developed for
complete discharge of plastic gas pipe.
INTERNAL DISHCARGER APPROACH
Three designs were investigated for the internal discharger; (1) a
cutting knife; (2) a heated needle; and (3) a modified tapping fitting.
The modified tapping fitting approach was successful and was recommended
for development by gas industry advisors.
Two important requirements of the discharger are that: (1) the unit cost
be $2,500 or less; and (2) the weight be 15.9 kg (35 pounds) or less.
Design
Figure
1 shows the prototype discharger system used in the first three pilot field
tests. For this design, a standard
reusable clamp-on self tapping TEE fitting was modified and used in a simple
design for the internal discharger.
In the design, the original cutter was replaced by a special cutter that has a
recessed side-mounted nozzle near the end.
The discharger cutter cuts a circular plug out of the pipe wall in the
same manner as the original cutter.
The discharger cutter is smaller in diameter than the original cutter, since a
threaded adapter sleeve is used for protecting the threads on the plastic
tapping TEE. The adapter sleeve
also provides a convenient point for grounding the cutter.
After penetrating the pipe from the side and centering the nozzle,
pressurized (typically 100 psi) antistatic fluid flows through the center of the
cutter body and out through a nozzle. A check valve on the cutter prevents any
gas from escaping to the atmosphere during the discharge procedure.
An inline filter within the threaded body of the cutter removes any
particles that might clog the nozzle. A toggle (lever) valve at the cutter is
used for applying the antistatic spray. A
rubber hose and a quick-disconnect fitting provide the hookup with the
pressurized canister (lecture bottle).
The discharger design uses mostly stainless steel components and is
estimated to have 8,000-10,000 hours MTBF.

Operation
In
operation, the self-tapping TEE is bolted on the pipe to be discharged.
The threaded sleeve is grounded through a braided-wire strap connected to
a stake screwed into the ground.
The cutter is screwed into the sleeve and turned clockwise (using a box-end
wrench) to penetrated the pipe wall.
Although penetration of the pipe wall can be either on the top or side,
the preferred orientation is through a sidewall.
After the cutter penetrates the pipe wall, it is further screwed into the
sleeve until the nozzle is centered in the pipe.
(The threads are marked to indicate when the nozzle is centered in the
pipe.) The nozzle rotates
(continuously) while applying the antistatic spray.
A typical discharge operation requires about 30-60ml (1-2 oz) of
antistatic fluid. Figure 2 shows
the discharger mounted on acrylic pipe as the nozzle is being rotated.
Generally, gas flow is cut off via squeeze off before discharging.
Spraying from the side occurs by rotating the nozzle in a 0-180 degree
upward arc either clockwise or counterclockwise.
As the nozzle rotates, the antistatic spray jet tracks the centerline of
the pipe over a ±61 cm (±2 foot) range under no-flow conditions.
After spraying along the centerline of the pipe, fluid then runs down the
sides of the pipe and uniformly coats the interior and makes contact with the
grounded metallic cutter. In
spraying from the top, the nozzle must rotate 0-360 degrees to cover the inside
surface of the pipe, and more fluid is required.
Clamp-On Fitting
After the first three pilot field tests, the discharger system was upgraded to include clamp-on saddle fittings and a purging capability. Figure 3 shows one of the modified fittings. This fitting reduces the setup time required to mount the discharger and eliminates an overtorque problem that occurred with the previous fitting. Purging enhances the safety of the discharge procedures.

EXTERNAL DISCHARGING APPROACH
After reviewing the technical literature, an antistatic PE film was
evaluated for the exterior charge problem.
The material used most extensively throughout the project was static
dissipative polyethylene that is available in 2-6 mil thicknesses of various
widths. Its original application is
for packaging electronic components, and it is typically manufactured in tubular
form (double thickness). In
application, the antistatic PE film is spiral-wrapped on the pipe after
grounding the starting end of a roll.
The loose end of the roll is then grounded after completing the final
warp. Grounding and wrapping
provide a conductive path for counter charger to flow from ground to neutralize
any excess exterior charge.
Application of the antistatic PE film eliminates:
(1) all external electric fields emanating from the pipe; (2) the
“solution of dishwasher-type detergent” and associated mess in the trench; (3)
frequent wetting applications in hot weather because of evaporation; and (4)
freezing problems in cold weather.
The PE-film wrap contains an internal amine-free, non-blooming organic
antistatic agent that is essentially unaffected by relative humidity.
ASTM4 standards for antistatic PE films require a surface
resistivity of typically 9 x 1011 ohms per square.
Tests on some antistatic PE-film specimens over 20 years in age show that
the resistivity characteristics of the material are unaffected by long shelf
life. Besides the PE-film wrap
having an intrinsic resistivity, the wrap is also useful in retaining and
preserving antistatic fluid films on the exterior.

INSTRUMENTATION APPROACH
Faraday Cage
For
the pipe application, the Faraday cage is a useful laboratory apparatus for
determining the interior voltage.
The Faraday cage design for the pipe application is a closed coaxial cylinder
around the pipe that provides a shielded chamber (annulus around the pipe) that
can be purged with nitrogen for limiting charge leakage on the pipe exterior.
Figure
4 shows the Faraday cage, which has a length of 61 cm (24 inches) and a diameter
of 25 cm (9.875 inches). The design
of the cage includes a circular cutout in the ends for 10-cm (4 inch) pipe.
Adapters can be fitted into the 10-cm (4-inch) cutout for use on other
pipe sizes. An electric field
sensor (Monroe Electronics 1019B) mounted on the outside wall at the center of
the cylinder measures electric fields emanating from the pipe.
The voltage inside the pipe is given by the expression:
V = kE
Where:
E = electric field (V/m) at the wall of the cylinder;
k = geometric factor (m) of the cage; or
k = 0.1237 for 10-cm (4-inch) pipe; and
k = 0.2039 for 5-cm (2-inch) pipe.
By purging the cage with nitrogen, good results were usually obtainable
in preventing exterior charge accumulations inside the cage, although some tests
showed residual charge effects following pipe discharge.

Flat
Plate Sensor
Figure
5 shows another useful sensor, which is a grounded flat plate mounted 18 cm (7.2
inches) above the centerline of the pipe.
An electric filed sensor (Monroe Electronics 1019B) at the center of the
41 x 61 cm (16 x 24 inches) plate measured electric fields emanating from the
pipe. The flat plate sensor is
applicable only as an uncalibrated instrument for assessing electric fields
exterior to the pipe and lacks provisions for preventing charge leakage on the
pipe exterior. The flat plate
sensor is ideal for monitoring electric fields during exterior charge
neutralization as an antistatic PE film is wrapped around the pipe.
Hand-Held Electric Fieldmeter
For field applications, the ACL Inc. Model 300B hand-held voltmeter was
used to detect the presence of charge on pipe.
Although this instrument can detect charge, it cannot accurately measure
voltage on the inside or outside because of the theoretical limitations
(described above) resulting from exterior chare masking the interior charge.
Therefore, a zero measurement obtained using this instrument does not
necessarily mean that a pipe is charge free.
ANTITSTATIC FLUID APPROACH
The antistatic fluid for discharging plastic gas pipe is a critical
component in the operation of the discharger, since it must not: (1) affect the
PE pipe by accelerating crack growth; (2) burn: or (3) product corrosion in gas
meters, etc. Although water can
dissipate charge somewhat, it forms beads on slick PE surfaces and does not coat
the surfaces uniformly. A
surfactant is necessary to produce a uniform coating on slick PE surfaces.
Generally, antistatic fluids consist mostly of water and will freeze.
To prevent freezing, an antifreeze additive is necessary.
A special formulation was developed that has proven effective in safely
neutralizing static charge accumulations and in meeting the gas industry
requirements. The fluid is a
noncorrosive, nontoxic, environmentally benign enzyme solution that can be used
with or without an equally benign and environmentally acceptable freezing–point
depressant (anti-freeze agent). The
enzyme solution is a commercially available degreasing cleaner, which is offered
as a concentrate. When diluted by
15-30 volumes of water per one volume of enzyme, the resulting solution
effectively dissipates static electricity and energy from plastic surfaces.

TEST FACILITIES
Three closed test loops were constructed from 10-cm (4-inch) pipes for
charging various types of PE pipe sections (HD and MD; 10 –cm and 5-cm
diameters) to determine the effectiveness of the new discharger technology.
Figure 6 shows a complex piping network that was used for the first test
loop. This loop included several
elbows and
Circulation of particulates is necessary for generating charge.
Particulates can be almost anything.
Based on experience, an inert-gas atmosphere is necessary to avoid an
explosion. This required purging the
system with nitrogen and maintaining a slightly positive pressure in the loop.
Although various particulates were tried, the most effective one was
Poly-grit® (blasting material), which is comprised of approximately 30-percent
iron oxide. This material is
preferred because of the iron oxide content, which is similar to materials found
in gas distribution pipes. Electric
fields approaching 80-percent breakdown (16kV/mm) were generated by using
Poly-grit®. As electric fields
increase from charging, corona discharge begins to occur within the pipes that
limits the charge levels attainable.
In circulating particulates in PE pipes, it is not always possible to predict
the polarity of the charge, since both positive and negative electric fields
were observed. The polarity of the
charge is not a factor in the operation of the discharger.
TEST RESULTS
A
total of 50 laboratory tests and four pilot field testes were conducted. The laboratory tests were accomplished using
three different test loops. The pilot
field testes were conducted at three different gas companies: (1) two at Minnegasco;
92) one at Mountain Fuel Supply Company; and (3) one at Lone Star Gas
Company. Because of the number of
laboratory and field tests conducted, only the most significant tests are
described in this section. The tests
fall in two categories: (1) external
wrap; and (2) internal discharge. All
laboratory tests conducted using the antistatic PE film showed that exterior
charge accumulations are neutralized by counter charge flowing from ground
along the conductive surface path of the film.
In applying antistatic spray in the interior of a pipe, unequivocal
neutralization occurs when the coating is uniform and counter charge flows from
ground, through the metallic cutter, to the interior of the pipe, which has
been made conductive. In conducting the
internal discharge tests, some low-level residual electric fields were observed
after completing prescribed discharge procedures. The most probable cause of any residual
effects is charge leakage (within the Faraday cage) to the exterior of the
pipe, which is difficult to control because of humidity conditions. Another probable factor for residual effects
is space charge5 within the pipe wall, since it has been shown that
high electric fields can induce residual space charge effects in PE
samples. Other factors that might affect
the outcome of a test include: (1)
initial charge magnitude, polarity, and distribution; and (2) different pipe
materials.
Low-level
residual electric fields are not considered significant or hazardous. In cases where this phenomenon occurred, no
charge was ever encountered while cutting a pipe following a discharge
test. If complete discharge is
accomplished where both the inner and outer surfaces are treated, the reduction
of the exterior resistivity masks any residual electric field effects that
otherwise would be observable.


Antistatic Wrap Test
The
flat plate sensor was mounted on 10-cm (4-inch) medium density (MD) pipe and
used for evaluating the effectiveness of the antistatic PE-film wrap.
The space between the pipe and the flat plate sensor allows the pipe to
be wrapped; therefore, electric field measurements can be made before and after
wrapping.
Exterior Charge After Internal Discharge
In one
discharge test conducted, the electric fields from the Faraday cage and flat
plate sensors were monitored simultaneously.
For this test, the Faraday cage was mounted upstream from the flat plate
sensor. After this test, a residual
field was observed at the flat plate sensor because of excess surface charge on
the pipe. The effects of
discharging the pipe internally are observable in the data from the flat plate
sensor downstream from the Faraday cage.
Excess surface charge of opposite polarity (negative) was left on the
pipe. After discharging the loop
internally, outside surface charge was evident by rubbing the test pipe
sections. Discharges were
experienced (felt and audible) during this process.
Figure 10 shows the two sensor responses during this test.
The data from the flat plate sensor show the masking effects of exterior
charge. Although the internal
conditions inside the pipe were neutralized (as shown by the Faraday cage data),
excess charge accumulated on the pipe exterior.
To an observer in a trench making a repair, the use of the discharger
would appear to increase the charge buildup on the pipe exterior.
Without lowering the surface resistivity of the pipe in some manner, the
free excess surface charge would greatly increase the hazard of external
discharge from the pipe.
Therefore, the discharger should never
bus used until proper precautions have been taken to treat the external surface
of the pipe. Treatment of the
pipe exterior will involve: (1) applying an antistatic spray (hand spray bottle)
or mist to the pipe; or (2) wrapping the pipe with the antistatic film.
First
Minnegasco Test
The
first Minnegasco test was conducted on a 10-cm (4-inch) main involving a two-way
feed. A break was simulated by a
tapping TEE and venting gas through a vent pipe.
No high-charge conditions were encountered during the discharge
procedure. However, the vent pipe
was slightly charged but was neutralized by the antistatic spray in the pipe.
A 1.5-by 2.1 meter (5- by 7-foot) trench approximately 1.8 m (6-feet)
deep was excavated to expose the pipe, which was buried at a depth of 1.6 m (62
inches). Figures 12 and 13 show a
diagram of the test site and the shoring box used in the trench.


Prior to discharging, the discharger was checked as shown in Figure 14.

Squeeze off was performed on each end of exposed pipe to stop gas flow.

Figure 15 shows the fusion tapping TEE installed on the main fro a 1.6-cm (5/8-inch) PE vent pipe to simulate the leak. The pie was wrapped using the antistatic PE film. Figure 16 shows the wrapped section of pipe between the squeeze-off tools.

The internal discharger was installed on the pipe approximately 41 cm (16 inches) upstream from the tapping TEE. This point was approximately 76 cm (2.5 feet) downstream from squeeze-off tool #1. The pipe was penetrated on the side as shown in Figure 17, and the antistatic spray was applied in a 360-degree rotation, starting from the top center of the pipe, spraying across the top of the pipe lengthwise upstream and then downstream.

TEST
CONCLUSIONS
The
test conclusions that can be drawn from the laboratory and pilot field tests
are listed below.
·
Using
developed technology discharger after squeeze off in a no-flow condition proved
to be effective and repeatable;
·
Both
inner and outer pipe surfaces must be discharged;
·
The
interior of the pipe can be successfully discharged using the modified tapping
TEE discharger and the antistatic fluid spray;
·
The
exterior charge can be neutralized by using the antistatic PE-film wrap;
·
Discharging
the pipe interior will increase the apparent hazard of external discharge if
the outer pipe surfaces is untreated;
·
Inner
discharge is more effective by applying the antistatic spray from the sidewall
and rotating the nozzle 0-180 degrees; and
·
Purging
is necessary because of possible discharge when pipe wall is penetrated.
FIELD COMMENTS
In conducting the pilot
field tests, participating personnel completed a questionnaire on
the equipment and procedures. The following is a summary of some of the
important field comments.
·
The
antistatic fluid and PE wrap appear to be superior for treating static problems
and have immediate field applications;
·
Field
personnel felt the discharger was a good system and would be useful in
repairing PE pipe;
·
The
antistatic PE-film wrap and antistatic fluid were well received;
·
The
discharger penetrates the pie wall easily;
·
Due
to space limitations in the trench, a right-angle adapter would be useful; and
·
A
quicker method was recommended for mounting the internal discharger. One alternative might be a tool using a ½
-rotation cam lock lever.
BENEFITS TO THE GAS
INDUSTRY
·
The
occurrence of electrostatic-related incidents will be eliminated or reduced
using the developed technology;
·
The
antistatic wrap and developed antistatic fluid are very inexpensive and total
field effective;
·
The
internal discharger is economical and reusable;
·
Personnel
safety will be substantially enhanced;
·
Potential
property damage will be significantly reduced;
·
PE
pipe repair can be accomplished with confidence knowing that all possible
safety precautions are being taken; and
·
The
antistatic fluid does not affect the PE pipe or the environment.
FINAL CONCLUSIONS
Charge
Problem: Unavoidable internal
charging induces external charge. The
presence of excess charge on either the inner or outer surfaces can result n a
spark discharge capable of igniting a flammable gas-air atmosphere;
Need: Before pipe repair begins, static charge must be
eliminated;
Solution: To eliminate charge problems, the internal and external
surface resistivities must be lowered so that counter charge can be produced
through a conductive ground path;
Benefits:
·
A
practical tool has been developed for the first time to neutralize internal
charge;
·
Methods
have been found to discharge the external surfaces more effectively than
present gas industry practices;
·
Discharging
can be accomplished safely; and
·
Electrostatic
incidents will be reduced using the new technology.
FUTURE PLANS
·
Manufactures
have been solicited to begin commercialization of developed discharger system;
·
The
system upgrade has been completed;
·
GRI
is selecting prospective vendors;
·
Additional
filed tests will be conducted for three months min9ijmum by various
participating gas companies;
·
The
purpose of the field testes is to optimize and field ruggedize the discharger
under blowing –gas conditions; and
·
Commercial
systems should be made available to the gas industry by April-May 1993.
REFERENCES
1.
Staker,
M., “Static Electric Pinholing Through Polyethelyene Pipe,” American Gas
Association Distribution Conference, May 22-24, 1989.
2.
OPSO
Report ID #870071, Delta Natural Gas Company, Inc., Corbin, Kentucky, 1987.
3.
American
Gas Association (AGA) Plastic Pipe Manual For Gas Service, Catalog No. XR8902,
Arlington, VA, February 1989.
4.
ASTM
Method D-257-78, DC Resistance or Conductance Of Insulating Materials.
5.
Patsch,
R., “Space Charge Phenomena In Polyethylene At High Electric Field,” J. Phys., D: Appl. Phys., Volume 23, 1990, pp.
1497-1505.
STEP-BY-STEP
FIELD PROCEDURES
FOR
DISCHARGING
PLASTIC GAS PIPE
Based on laboratory tests, a
preliminary discharge procedure, consisting of a sequence of steps, was devised
for the pilot field tests. These preliminary
steps were further revised because of the pilot field test results to include
provisions for absolute pinhole protection and for purging. A single discharge procedure is not entirely
feasible for all leak situations because of differing requirements of each gas
company. For example, some gas companies
are not concerned with the pinhole problem.
It is believed that cutting the gas off (via squeeze-off) is the highest
priority for most gas companies when arriving at the scene of a leak. Because of different requirements, the
following discharge steps are only intended to be a general guide in
approaching a field problem. Any step
that is not applicable to a specific field repair situation can be omitted. It is anticipated that as more experience is
gained with the discharger under blowing gas conditions in the
commercialization phase of the project, further revisions will occur before the
final discharge procedure emerges. The
equipment needed for discharging includes:
(1) a roll of antistatic PE film;
(2) two internal discharger units; an d(3) a spray bottle of antistatic
fluid. The antistatic fluid used for
discharging is a special formulation developed on the project that does not
freeze, or evaporate, or affect the plastic pipe.
Step 1 - Third Party Damage
Step 1 involves third party damage
such as a gouge or a puncture in the pipe that causes a leak. At this point in the repair scenario, the
pipe is buried, but the hole in the pipe is visible, and the gas is escaping. A dust cloud probably results from the
escaping gas, and it is very likely that high-charge conditions occur around
the lip of the hole.
Step 2 - Excavation of Bellholes
The objective of the step is to shut
off the gas flow by digging bellholes (±3 meters, minimum, from leak) and
squeezing the pipe on either side of the leak.
In exposing the pipe in these bellholes, exterior charge accumulations
will occur if the pipe interior is charged.
An exterior application of antistatic spray using a hand-spray bottle
prevents undesirable spark discharges.
Step 3 - Pin hole Prevention At Bellhole
#1
In some regions, pinholing might be
a problem in performing squeeze-off operations.
Interior discharging in the squeeze-off area is necessary to prevent
pinholing. However, in performing this
step, it will not be known how effective the spray will be unless an estimate
is available on the flow conditions within the pipe. Penetration of the pipe wall with the
discharger is between the squeeze-off point and the leak. The distance from squeeze off to the
penetration point is typically five pipe diameters, minimum. The discharger remains in place after
neutralizing the potential pinhole area.
Note: Although the discharger is shown in a vertical position for
illustration purposes, the preferred penetration orientation is from the
side.
Step 4 - Squeeze Off At Bellhole #1
Following interior discharge in the
squeeze-off area, the pipe is squeezed off to stop gas flow (at least in one
direction). Gas will continue to escape
from the leak until the other side of the pipe is squeezed off; however, at
this point, gas flow probably will diminish.
Step 5 - Pinhole Prevention At Bellhole
#2
Pinhole
prevention also may be necessary in Bellhole #2. Using the second discharger unit, penetration
occurs between the squeeze-off point and the leak at least five pipe diameters
from the squeeze-off point. After
discharging the squeeze-off area, the discharger remains in place. Like Step 3, it may be uncertain how
effective the antistatic spray is unless information is available on the flow
conditions, including direction of flow.
Note: Although the discharger is
shown in a vertical position for illustration purposes, the preferred
penetration orientation is from the side.
Step 6 - Squeeze Off At Bellhole #2
Squeeze off at Bellhole #2 completes
the gas shut off process. After squeeze
off and gas cutoff, the gas cloud disperses so that repair can begin in the
trench where the leak exists.
Step 7 - Pipe Excavation
After the gas cloud disperses, application
of antistatic spray (from a hand-spray bottle) neutralizes any high-charge
conditions that might exist around the lip of the leak.
Step 8 - Pipe Excavation
Application of antistatic spray
(from a hand-spray bottle) continues in excavating and exposing untreated pipe
surfaces in the repair trench. If the
wetted surfaces are grounded, then the antistatic spray treatment will be
sufficient in making the exterior of the pipe conductive for neutralizing any
exterior chare accumulations. This is true only for the special antistatic
fluid formulation developed on the project that does not evaporate or freeze. The exterior treatment of antistatic fluid
also augments the effectiveness of the antistatic PE film. The combined fluid treatment and the antistatic
PE-film wrap provide two conductive paths for the pipe exterior. The PE-film wrap also traps the moisture from
the spray treatment.
Step 9 - External Discharge
The external discharge process
begins by grounding the free end of a roll of the antistatic PE film or
covering the end with dirt. A piece of
double-sided carpet tape (or equivalent) may be necessary for securing the
first and last wraps around the pipe.
Spiral wrapping the entire length of pipe in the trench allows counter
charge from ground to neutralize the excess exterior charge. Burying the last-wrap end (cut to length) of
the antistatic PE film provides additional grounding for the wrap.
Step 10 - Purge Repair Section
The penetration holes used for
pinhole protection shown in Step 3 and Step 5 are also necessary for purging in
the preferred manner shown in Step 10.
The dischargers are replaced in this step by the purging saddles. Nitrogen is then used for purging
simultaneously at both bellholes. The
purging process should continue until the interior of the pipe is sprayed and
neutralized near the leak.
Step 11 - Internal Discharge
Step 11 shows: (1) the squeeze-off operation in the
bellholes; (2) purging from the bellholes; (3) the antistatic wrap for exterior
charge neutralization; and (4) the repair setup for interior discharging. Grounded dischargers penetrate the pipe on
either side of the leak (middle of pipe) and apply antistatic spray in both
directions. Audible arcing during
spraying indicates successful interior charge neutralization. The penetration point is 30-61 cm (1-2 feet)
from the leak. Although the dischargers
are penetrating through the top of the pipe in the illustration, the preferred
penetration point is through a sidewall.
Step 12 - Remove Dischargers and Wrap
After accomplishing complete
discharge, the dischargers and antistatic PE wrap are removed. Also at this point, the purging source
(nitrogen gas) can be shut off.
Step 13 - Remove Damaged Pipe Section
Since the pipe is totally neutralized
at this point, the repair process proceeds by cutting and removing the
defective pipe section. The pipe to be
cut contains the holes from the dischargers; therefore, no repair procedures
are necessary for these holes.
Step 14 - Pipe Repair
The pipe repair is completed by
using conventional techniques. In the
bellholes, fusion saddle fittings are installed over the holes made by the
dischargers. The saddle fittings are
convenient for purging as required in the next step and for repairing the discharger
holes.
Step 15 - Vent New Pipe Section
Many gas companies do not release
air in a line resulting from a repair.
Step 15 shows the right squeeze-off tool slightly released so that the
repaired section of pipe can be vented.
The venting process can be accomplished from points 1-3 or 3-1.
Step 16 - Fill Bellholes And Repair
Trench
After venting, both saddle fittings
are capped, and both squeeze-off tools are removed to reestablish service. The final step is to backfill the repair
trench and the bellholes.
ALTERNATE PROCEDURE FOR PINHOLE
PREVENTION
When the direction of the gas flow
is know, alternative discharge steps can be followed to insure that pinhole
protection is achieved in the squeeze-off areas. In pursing the alternative discharge steps,
Steps 1 and 2 would be performed first as described above. These steps are followed by Step 3A and the
succeeding steps described below.
Step 3A - Spray Downstream
Like Step 3, the pipe is penetrated
by the discharger in the left bellhole, and the antistatic spray is directed
downstream stream (or with the gas flow) in the area where squeeze-off will
occur.
Step 3B - Spray Upstream
After the squeeze-off area has been
sprayed downstream, the pipe is then squeezed off, and the discharger nozzle is
directed upstream under no-flow conditions.
Step 3C - Double Squeeze Off
A second squeeze-off tool is used in
the left bellhole in a double squeeze-off operation.
Step 3D - Remove Squeeze-Off Tool
The first squeeze-off tool is then
removed as shown in Step 3D. This
configuration is the same as shown in Step 4, previously described.
Continuation of Discharge Process
Because of backpressure and escaping
gas downstream, the alternative steps (3A-3D) would be repeated in lieu of Step
5 described above. When the second set
of alternative steps is completed, the original steps would be continued,
beginning at Step 7.
Alternative Purge Sequence
The overall discharge procedure can
be greatly simplified if there is no concern for pinhole protection. Figure 38 shows the simplified trench
configuration. This configuration is
also compatible with the viewpoint held by most gas companies where the highest
priority is to shut the gas off as quickly as possible (via squeeze off) when
arriving at the leak site.
In the simplified procedure,
bellholes would be excavated and the gas shut off via squeeze off. Following this critical step, antistatic
spray would then be applied around the lip of the
gouge to discharge any high point charges that would probably occur. Small-diameter plastic tubing would then be
inserted into the pipe like a catheter for purging. These purging tubes would extend up to the
squeeze-off points. After the purging tubes are in place, nitrogen would be used
to displace any gas-air mixture residing within the pipe. Purging occurs from within the pipe through
the gouge hole as nitrogen fills the interior of the pipe.
From this point, the trench is fully
excavated for repairing the pipe. The
exposed exterior surfaces are treated by the antistatic spray and wrapped with
the antistatic PE film to discharge the exterior surface as shown in Step 9
(figure 27). Steps 11-13 (Figures 29-31)
then follow in the procedure.
If there is no concern about
venting, the squeeze-off tools are removed, and the trench and bellholes are
backfilled in restoring service. If
venting is necessary, a tapping saddle must be installed for this purpose.